October update

10 months ago

Redevelopment works are now underway with the main building and outdoor pool demolished last week.

Site clearing is expected to be completed by late November and then site excavation and piling will begin. These works are due to be completed in mid-February.

Works will take place from Monday to Saturday and are anticipated to shut down during the Christmas and New Year period.

We’ll be sharing progress updates throughout the build so make sure to subscribe for updates using the Stay Informed button below right.